Startseite Partner Suche Impressum Kontakt Diskussionsforum

-

-

Aktuelle Jobs

-

 

Jobbörse

 

-

Allgemein

-

 

Diskussionsforum

 

 

IFRS/IAS  

 

Newsletter  

Musterabschluss

Abschlüsse

-

Dienstleistungen

-

 

IFRS Anwendergruppe

 

 

Umstellungen auf IFRS  

Software/IFRS-Toolkit

-

Grundlagen

-

 

Was sind IFRS/IAS?

 

 

Was ist der IASB?  

 

Umstellungsprozess  

 

Endorsement  

Glossar

-

Mittelstand

-

 

IFRS für KMU  

-

Literatur

-

 

Presse

 

 

Aufsatzdatenbank  

 

Fachbücher  

Broschüren

-

Texte deutsch

-

 

Framework

 

 

Standards  

Interpretations

-

Texte englisch

-

 

Framework

 

 

Standards  

Interpretations

-

Sonstiges

-

 

Gästebuch

 

 

Archive  

 

Links  

 

Über uns  

Sitemap


-

INTERNATIONAL ACCOUNTING STANDARD 11 (2006)

Previous | Index | Next

  Source

-

Commission Regulation (EC) No 1725/2003 of 29 September 2003 adopting certain international accounting standards in accordance with Regulation (EC) No 1606/2002 of the European Parliament and of the Council

  Content

-

Contract costs

16. Contract costs should comprise:

(a) costs that relate directly to the specific contract;

(b) costs that are attributable to contract activity in general and can be allocated to the contract; and

(c) such other costs as are specifically chargeable to the customer under the terms of the contract.

17. Costs that relate directly to a specific contract include:

(a) site labour costs, including site supervision;

(b) costs of materials used in construction;

(c) depreciation of plant and equipment used on the contract;

(d) costs of moving plant, equipment and materials to and from the contract site;

(e) costs of hiring plant and equipment;

(f) costs of design and technical assistance that is directly related to the contract;

(g) the estimated costs of rectification and guarantee work, including expected warranty costs; and

(h) claims from third parties.

These costs may be reduced by any incidental income that is not included in contract revenue, for example income from the sale of surplus materials and the disposal of plant and equipment at the end of the contract.

18. Costs that may be attributable to contract activity in general and can be allocated to specific contracts include:

(a) insurance;

(b) costs of design and technical assistance that is not directly related to a specific contract; and

(c) construction overheads.

Such costs are allocated using methods that are systematic and rational and are applied consistently to all costs having similar characteristics. The allocation is based on the normal level of construction activity. Construction overheads include costs such as the preparation and processing of construction personnel payroll. Costs that may be attributable to contract activity in general and can be allocated to specific contracts also include borrowing costs when the contractor adopts the allowed alternative treatment in IAS 23, borrowing costs.

19. Costs that are specifically chargeable to the customer under the terms of the contract may include some general administration costs and development costs for which reimbursement is specified in the terms of the contract.

20. Costs that cannot be attributed to contract activity or cannot be allocated to a contract are excluded from the costs of a construction contract. Such costs include:

(a) general administration costs for which reimbursement is not specified in the contract;

(b) selling costs;

(c) research and development costs for which reimbursement is not specified in the contract; and

(d) depreciation of idle plant and equipment that is not used on a particular contract.

21. Contract costs include the costs attributable to a contract for the period from the date of securing the contract to the final completion of the contract. However, costs that relate directly to a contract and which are incurred in securing the contract are also included as part of the contract costs if they can be separately identified and measured reliably and it is probable that the contract will be obtained. When costs incurred in securing a contract are recognised as an expense in the period in which they are incurred, they are not included in contract costs when the contract is obtained in a subsequent period.

Recognition of contract revenue and expenses

22. When the outcome of a construction contract can be estimated reliably, contract revenue and contract costs associated with the construction contract should be recognised as revenue and expenses respectively by reference to the stage of completion of the contract activity at the balance sheet date. An expected loss on the construction contract should be recognised as an expense immediately in accordance with paragraph 36.

23. In the case of a fixed price contract, the outcome of a construction contract can be estimated reliably when all the following conditions are satisfied:

(a) total contract revenue can be measured reliably;

(b) it is probable that the economic benefits associated with the contract will flow to the enterprise;

(c) both the contract costs to complete the contract and the stage of contract completion at the balance sheet date can be measured reliably; and

(d) the contract costs attributable to the contract can be clearly identified and measured reliably so that actual contract costs incurred can be compared with prior estimates.

24. In the case of a cost plus contract, the outcome of a construction contract can be estimated reliably when all the following conditions are satisfied:

(a) it is probable that the economic benefits associated with the contract will flow to the enterprise; and

(b) the contract costs attributable to the contract, whether or not specifically reimbursable, can be clearly identified and measured reliably.

25. The recognition of revenue and expenses by reference to the stage of completion of a contract is often referred to as the percentage of completion method. Under this method, contract revenue is matched with the contract costs incurred in reaching the stage of completion, resulting in the reporting of revenue, expenses and profit which can be attributed to the proportion of work completed. This method provides useful information on the extent of contract activity and performance during a period.

26. Under the percentage of completion method, contract revenue is recognised as revenue in the income statement in the accounting periods in which the work is performed. Contract costs are usually recognised as an expense in the income statement in the accounting periods in which the work to which they relate is performed. However, any expected excess of total contract costs over total contract revenue for the contract is recognised as an expense immediately in accordance with paragraph 36.

27. A contractor may have incurred contract costs that relate to future activity on the contract. Such contract costs are recognised as an asset provided it is probable that they will be recovered. Such costs represent an amount due from the customer and are often classified as contract work in progress.

28. The outcome of a construction contract can only be estimated reliably when it is probable that the economic benefits associated with the contract will flow to the enterprise. However, when an uncertainty arises about the collectability of an amount already included in contract revenue, and already recognised in the income statement, the uncollectable amount or the amount in respect of which recovery has ceased to be probable is recognised as an expense rather than as an adjustment of the amount of contract revenue.

29. An enterprise is generally able to make reliable estimates after it has agreed to a contract which establishes:

(a) each party's enforceable rights regarding the asset to be constructed;

(b) the consideration to be exchanged; and

(c) the manner and terms of settlement.

It is also usually necessary for the enterprise to have an effective internal financial budgeting and reporting system. The enterprise reviews and, when necessary, revises the estimates of contract revenue and contract costs as the contract progresses. The need for such revisions does not necessarily indicate that the outcome of the contract cannot be estimated reliably.

30. The stage of completion of a contract may be determined in a variety of ways. The enterprise uses the method that measures reliably the work performed. Depending on the nature of the contract, the methods may include:

(a) the proportion that contract costs incurred for work performed to date bear to the estimated total contract costs;

(b) surveys of work performed; or

(c) completion of a physical proportion of the contract work.

Progress payments and advances received from customers often do not reflect the work performed.

31. When the stage of completion is determined by reference to the contract costs incurred to date, only those contract costs that reflect work performed are included in costs incurred to date. Examples of contract costs which are excluded are:

(a) contract costs that relate to future activity on the contract, such as costs of materials that have been delivered to a contract site or set aside for use in a contract but not yet installed, used or applied during contract performance, unless the materials have been made specially for the contract; and

(b) payments made to subcontractors in advance of work performed under the subcontract.

32. When the outcome of a construction contract cannot be estimated reliably:

(a) revenue should be recognised only to the extent of contract costs incurred that it is probable will be recoverable; and

(b) contract costs should be recognised as an expense in the period in which they are incurred.

An expected loss on the construction contract should be recognised as an expense immediately in accordance with paragraph 36.

33. During the early stages of a contract it is often the case that the outcome of the contract cannot be estimated reliably. Nevertheless, it may be probable that the enterprise will recover the contract costs incurred. Therefore, contract revenue is recognised only to the extent of costs incurred that are expected to be recoverable. As the outcome of the contract cannot be estimated reliably, no profit is recognised. However, even though the outcome of the contract cannot be estimated reliably, it may be probable that total contract costs will exceed total contract revenues. In such cases, any expected excess of total contract costs over total contract revenue for the contract is recognised as an expense immediately in accordance with paragraph 36.

34. Contract costs that are not probable of being recovered are recognised as an expense immediately. Examples of circumstances in which the recoverability of contract costs incurred may not be probable and in which contract costs may need to be recognised as an expense immediately include contracts:

(a) which are not fully enforceable, that is, their validity is seriously in question;

(b) the completion of which is subject to the outcome of pending litigation or legislation;

(c) relating to properties that are likely to be condemned or expropriated;

(d) where the customer is unable to meet its obligations; or

(e) where the contractor is unable to complete the contract or otherwise meet its obligations under the contract.

35. When the uncertainties that prevented the outcome of the contract being estimated reliably no longer exist, revenue and expenses associated with the construction contract should be recognised in accordance with paragraph 22 rather than in accordance with paragraph 32.

 

Previous | Index | Next

 


 

Anzeige

Newsletter:

Name

E-Mail

-

Partner

-

RöverBrönner KG

-

Mediadaten

-

 

Zugriffszahlen

 

Onlinewerbung

-

Veranstalter

-

 

AvenDATA GmbH

 

 

Digitale Signatur

 

 

GDPdU Portal

 

 

Unternehmens-nachfolge

 

 

Verfahrens-dokumentation

 

 

AvenDATA GmbH. Kaiserin-Augusta-Allee 14 . D-10553 Berlin . Deutschland
  Tel +49 30 700 157 500 . Fax +49 30 700 157 599  . E-mail: webmaster@ifrs-portal.com