|
Commission Regulation (EC) No 1725/2003
of 29 September 2003
adopting certain international accounting standards in
accordance with Regulation (EC) No 1606/2002
of the European Parliament and of the Council
Content |
|
- |
Reimbursements
53. Where some or all of the
expenditure required to settle a provision is expected to be
reimbursed by another party, the reimbursement should be
recognised when, and only when, it is virtually certain that
reimbursement will be received if the enterprise settles the
obligation. The reimbursement should be treated as a separate
asset. The amount recognised for the reimbursement should not
exceed the amount of the provision.
54. In the income statement,
the expense relating to a provision may be presented net of
the amount recognised for a reimbursement.
55. Sometimes, an enterprise is
able to look to another party to pay part or all of the
expenditure required to settle a provision (for example,
through insurance contracts, indemnity clauses or suppliers'
warranties). The other party may either reimburse amounts paid
by the enterprise or pay the amounts directly.
56. In most cases the enterprise
will remain liable for the whole of the amount in question so
that the enterprise would have to settle the full amount if
the third party failed to pay for any reason. In this
situation, a provision is recognised for the full amount of
the liability, and a separate asset for the expected
reimbursement is recognised when it is virtually certain that
reimbursement will be received if the enterprise settles the
liability.
57. In some cases, the enterprise
will not be liable for the costs in question if the third
party fails to pay. In such a case the enterprise has no
liability for those costs and they are not included in the
provision.
58. As noted in paragraph 29, an
obligation for which an enterprise is jointly and severally
liable is a contingent liability to the extent that it is
expected that the obligation will be settled by the other
parties.
Changes in provisions
59. Provisions should be
reviewed at each balance sheet date and adjusted to reflect
the current best estimate. If it is no longer probable that an
outflow of resources embodying economic benefits will be
required to settle the obligation, the provision should be
reversed.
60. Where discounting is used,
the carrying amount of a provision increases in each period to
reflect the passage of time. This increase is recognised as
borrowing cost.
Use of provisions
61. A provision should be used
only for expenditures for which the provision was originally
recognised.
62. Only expenditures that relate
to the original provision are set against it. Setting
expenditures against a provision that was originally
recognised for another purpose would conceal the impact of two
different events.
Application of the recognition and measurement rules
Future operating losses
63. Provisions should not be
recognised for future operating losses.
64. Future operating losses do
not meet the definition of a liability in paragraph 10 and the
general recognition criteria set out for provisions in
paragraph 14.
65. An expectation of future
operating losses is an indication that certain assets of the
operation may be impaired. An enterprise tests these assets
for impairment under IAS 36, impairment of assets.
Onerous contracts
66. If an enterprise has a
contract that is onerous, the present obligation under the
contract should be recognised and measured as a provision.
67. Many contracts (for example,
some routine purchase orders) can be cancelled without paying
compensation to the other party, and therefore there is no
obligation. Other contracts establish both rights and
obligations for each of the contracting parties. Where events
make such a contract onerous, the contract falls within the
scope of this Standard and a liability exists which is
recognised. Executory contracts that are not onerous fall
outside the scope of this Standard.
68. This Standard defines an
onerous contract as a contract in which the unavoidable costs
of meeting the obligations under the contract exceed the
economic benefits expected to be received under it. The
unavoidable costs under a contract reflect the least net cost
of exiting from the contract, which is the lower of the cost
of fulfilling it and any compensation or penalties arising
from failure to fulfil it.
69. Before a separate provision
for an onerous contract is established, an enterprise
recognises any impairment loss that has occurred on assets
dedicated to that contract (see IAS 36, impairment of assets).
Restructuring
70. The following are examples of
events that may fall under the definition of restructuring:
(a) sale or termination of a line
of business;
(b) the closure of business
locations in a country or region or the relocation of business
activities from one country or region to another;
(c) changes in management
structure, for example, eliminating a layer of management; and
(d) fundamental reorganisations
that have a material effect on the nature and focus of the
enterprise's operations.
71. A provision for restructuring
costs is recognised only when the general recognition criteria
for provisions set out in paragraph 14 are met. Paragraphs 72
to 83 set out how the general recognition criteria apply to
restructurings.
72. A constructive obligation
to restructure arises only when an enterprise:
(a) has a detailed formal plan
for the restructuring identifying at least:
(i) the business or part of a
business concerned;
(ii) the principal locations
affected;
(iii) the location, function,
and approximate number of employees who will be compensated
for terminating their services;
(iv) the expenditures that
will be undertaken; and
(v) when the plan will be
implemented; and
(b) has raised a valid
expectation in those affected that it will carry out the
restructuring by starting to implement that plan or announcing
its main features to those affected by it.
73. Evidence that an enterprise
has started to implement a restructuring plan would be
provided, for example, by dismantling plant or selling assets
or by the public announcement of the main features of the
plan. A public announcement of a detailed plan to restructure
constitutes a constructive obligation to restructure only if
it is made in such a way and in sufficient detail (i.e.
setting out the main features of the plan) that it gives rise
to valid expectations in other parties such as customers,
suppliers and employees (or their representatives) that the
enterprise will carry out the restructuring.
74. For a plan to be sufficient
to give rise to a constructive obligation when communicated to
those affected by it, its implementation needs to be planned
to begin as soon as possible and to be completed in a
timeframe that makes significant changes to the plan unlikely.
If it is expected that there will be a long delay before the
restructuring begins or that the restructuring will take an
unreasonably long time, it is unlikely that the plan will
raise a valid expectation on the part of others that the
enterprise is at present committed to restructuring, because
the timeframe allows opportunities for the enterprise to
change its plans.
75. A management or
board decision to restructure taken before the balance sheet
date does not give rise to a constructive obligation at the
balance sheet date unless the entity has, before the balance
sheet date:
(a) started to
implement the restructuring plan; or
(b) announced the
main features of the restructuring plan to those affected by
it in a sufficiently specific manner to raise a valid
expectation in them that the entity will carry out the
restructuring.
If an entity starts
to implement a restructuring plan, or announces its main
features to those affected, only after the balance sheet date,
disclosure is required under IAS 10 Events after the
Balance Sheet Date, if the restructuring is material and
non-disclosure could influence the economic decisions of users
taken on the basis of the financial statements.
76. Although a constructive
obligation is not created solely by a management decision, an
obligation may result from other earlier events together with
such a decision. For example, negotiations with employee
representatives for termination payments, or with purchasers
for the sale of an operation, may have been concluded subject
only to board approval. Once that approval has been obtained
and communicated to the other parties, the enterprise has a
constructive obligation to restructure, if the conditions of
paragraph 72 are met.
77. In some countries, the
ultimate authority is vested in a board whose membership
includes representatives of interests other than those of
management (e.g. employees) or notification to such
representatives may be necessary before the board decision is
taken. Because a decision by such a board involves
communication to these representatives, it may result in a
constructive obligation to restructure.
78. No obligation arises for
the sale of an operation until the enterprise is committed to
the sale, i.e. there is a binding sale agreement.
79. Even when an enterprise has
taken a decision to sell an operation and announced that
decision publicly, it cannot be committed to the sale until a
purchaser has been identified and there is a binding sale
agreement. Until there is a binding sale agreement, the
enterprise will be able to change its mind and indeed will
have to take another course of action if a purchaser cannot be
found on acceptable terms. When the sale of an operation is
envisaged as part of a restructuring, the assets of the
operation are reviewed for impairment, under IAS 36,
impairment of assets. When a sale is only part of a
restructuring, a constructive obligation can arise for the
other parts of the restructuring before a binding sale
agreement exists.
80. A restructuring provision
should include only the direct expenditures arising from the
restructuring, which are those that are both:
(a) necessarily entailed by
the restructuring; and
(b) not associated with the
ongoing activities of the enterprise.
81. A restructuring provision
does not include such costs as:
(a) retraining or relocating
continuing staff;
(b) marketing; or
(c) investment in new systems
and distribution networks.
These expenditures relate to
the future conduct of the business and are not liabilities for
restructuring at the balance sheet date. Such expenditures are
recognised on the same basis as if they arose independently of
a restructuring.
82. Identifiable future operating
losses up to the date of a restructuring are not included in a
provision, unless they relate to an onerous contract as
defined in paragraph 10.
83. As required by paragraph 51,
gains on the expected disposal of assets are not taken into
account in measuring a restructuring provision, even if the
sale of assets is envisaged as part of the restructuring.
Previous |
Index |
Next
|