Content |
|
- |
Expected Cash Flow Approach
A7. The expected cash flow approach is,
in some situations, a more effective measurement tool than
the traditional approach. In developing a measurement, the
expected cash flow approach uses all expectations about
possible cash flows instead of the single most likely cash
flow. For example, a cash flow might be CU100, CU200 or
CU300 with probabilities of 10 per cent, 60 per cent and 30
per cent, respectively. The expected cash flow is CU220. The
expected cash flow approach thus differs from the
traditional approach by focusing on direct analysis of the
cash flows in question and on more explicit statements of
the assumptions used in the measurement.
A8. The expected cash flow approach
also allows use of present value techniques when the timing
of cash flows is uncertain. For example, a cash flow of CU1
000 may be received in one year, two years or three years
with probabilities of 10 per cent, 60 per cent and 30 per
cent, respectively. The example below shows the computation
of expected present value in that situation.
|
Present value
of CU1 000 in 1 year at 5%
|
CU952.38
|
|
|
Probability
|
10,00 %
|
CU95.24
|
|
|
|
|
|
Present value
of CU1 000 in 2 years at 5.25 %
|
CU902.73
|
|
|
Probability
|
60,00 %
|
CU541.64
|
|
|
|
|
|
Present value
of CU1 000 in 3 years at 5.50 %
|
CU851.61
|
|
|
Probability
|
30,00 %
|
CU255.48
|
|
|
|
|
|
Expected present value
|
|
CU892.36
|
A9. The expected present value of
CU892.36 differs from the traditional notion of a best
estimate of CU902.73 (the 60 per cent probability). A
traditional present value computation applied to this
example requires a decision about which of the possible
timings of cash flows to use and, accordingly, would not
reflect the probabilities of other timings. This is because
the discount rate in a traditional present value computation
cannot reflect uncertainties in timing.
A10. The use of probabilities is an
essential element of the expected cash flow approach. Some
question whether assigning probabilities to highly
subjective estimates suggests greater precision than, in
fact, exists. However, the proper application of the
traditional approach (as described in paragraph A6) requires
the same estimates and subjectivity without providing the
computational transparency of the expected cash flow
approach.
A11. Many estimates developed in
current practice already incorporate the elements of
expected cash flows informally. In addition, accountants
often face the need to measure an asset using limited
information about the probabilities of possible cash flows.
For example, an accountant might be confronted with the
following situations:
(a) the estimated amount falls
somewhere between CU50 and CU250, but no amount in the
range is more likely than any other amount. Based on
that limited information, the estimated expected cash
flow is CU150 [(50 + 250)/2].
(b) the estimated amount falls
somewhere between CU50 and CU250, and the most likely
amount is CU100. However, the probabilities attached to
each amount are unknown. Based on that limited
information, the estimated expected cash flow is
CU133.33 [(50 + 100 + 250)/3].
(c) the estimated amount will be
CU50 (10 per cent probability), CU250 (30 per cent
probability), or CU100 (60 per cent probability). Based
on that limited information, the estimated expected cash
flow is CU140 [(50 × 0.10) + (250 × 0.30) + (100 ×
0.60)].
In each case, the estimated expected
cash flow is likely to provide a better estimate of value in
use than the minimum, most likely or maximum amount taken
alone.
A12. The application of an expected
cash flow approach is subject to a costbenefit constraint.
In some cases, an entity may have access to extensive data
and may be able to develop many cash flow scenarios. In
other cases, an entity may not be able to develop more than
general statements about the variability of cash flows
without incurring substantial cost. The entity needs to
balance the cost of obtaining additional information against
the additional reliability that information will bring to
the measurement.
A13. Some maintain that expected cash
flow techniques are inappropriate for measuring a single
item or an item with a limited number of possible outcomes.
They offer an example of an asset with two possible outcomes:
a 90 per cent probability that the cash flow will be CU10
and a 10 per cent probability that the cash flow will be CU1
000. They observe that the expected cash flow in that
example is CU109 and criticise that result as not
representing either of the amounts that may ultimately be
paid.
A14. Assertions like the one just
outlined reflect underlying disagreement with the
measurement objective. If the objective is accumulation of
costs to be incurred, expected cash flows may not produce a
representationally faithful estimate of the expected cost.
However, this Standard is concerned with measuring the
recoverable amount of an asset. The recoverable amount of
the asset in this example is not likely to be CU10, even
though that is the most likely cash flow. This is because a
measurement of CU10 does not incorporate the uncertainty of
the cash flow in the measurement of the asset. Instead, the
uncertain cash flow is presented as if it were a certain
cash flow. No rational entity would sell an asset with these
characteristics for CU10.
Discount Rate
A15. Whichever approach an entity
adopts for measuring the value in use of an asset, interest
rates used to discount cash flows should not reflect risks
for which the estimated cash flows have been adjusted.
Otherwise, the effect of some assumptions will be
double-counted.
A16. When an asset-specific rate is
not directly available from the market, an entity uses
surrogates to estimate the discount rate. The purpose is to
estimate, as far as possible, a market assessment of:
(a) the time value of money for
the periods until the end of the asset’s useful life;
and
(b) factors (b), (d) and (e)
described in paragraph A1, to the extent those factors
have not caused adjustments in arriving at estimated
cash flows.
A17. As a starting point in making
such an estimate, the entity might take into account the
following rates:
(a) the entity’s weighted average
cost of capital determined using techniques such as the
Capital Asset Pricing Model;
(b) the entity’s incremental
borrowing rate; and
(c) other market borrowing rates.
A18. However, these rates must be
adjusted:
(a) to reflect the way that the
market would assess the specific risks associated with
the asset’s estimated cash flows; and
(b) to exclude risks that are not
relevant to the asset’s estimated cash flows or for
which the estimated cash flows have been adjusted.
Consideration should be given to risks
such as country risk, currency risk and price risk.
A19. The discount rate is independent
of the entity’s capital structure and the way the entity
financed the purchase of the asset, because the future cash
flows expected to arise from an asset do not depend on the
way in which the entity financed the purchase of the asset.
A20. Paragraph 55 requires the
discount rate used to be a pre-tax rate. Therefore, when the
basis used to estimate the discount rate is post-tax, that
basis is adjusted to reflect a pre-tax rate.
A21. An entity normally uses a single
discount rate for the estimate of an asset’s value in use.
However, an entity uses separate discount rates for
different future periods where value in use is sensitive to
a difference in risks for different periods or to the term
structure of interest rates.
Previous |
Index
|